Baseball Construction Update From VMI Athletic Director Donny White

The baseball stadium is coming along. The lights have been installed and it transforms the facility's appearance. The stadium will seat over 1300 and will have box seat areas on both the first and third base sides. An upper deck will be located along the first base side. The hill has been blasted and is getting close to being ready to accept the precast concrete structures that will make up the base for the seats, press box, and bathroom and concession building. The project will cost more than 4 million dollars.

Donny White
May, 2006